BOQ format: how to prepare a bill of quantities, with an example
The standard layout of a bill of quantities in Pakistan, how items are grouped and measured, a worked example, and how the BOQ drives every running bill.
A bill of quantities (BOQ) is the list of every item of work in a project, each with its unit and measured quantity, and, once priced, its rate and amount. The client uses it to compare tenders on the same basis; the contractor uses it to price the job; and after award it becomes the measure against which every running bill is paid.
Because the BOQ outlives the tender by years, its format matters more than most estimators think. An item described loosely at tender becomes an argument at the third running bill. This guide sets out the usual format in Pakistan and shows a small worked example.
The columns of a BOQ
Column
What it holds
Item no.
A number within its bill or section, for example 3.04
Description
What the work is, its material and specification, and what the rate includes
Unit
The unit of measurement: m³, m², m, kg, tonne, No., or a lump sum
Quantity
The measured quantity from the drawings
Rate
The price per unit, in PKR
Amount
Quantity × rate
The standard BOQ columns
How a BOQ is organised
A BOQ is split into bills or sections that follow the order of the work, each with its own subtotal, and a summary page that adds them up. A typical building BOQ in Pakistan runs:
General items and preliminaries: site setup, temporary works, insurance, mobilisation.
Services: plumbing, sanitary, electrical, often as separate bills or by specialist subcontractors.
External works, then provisional sums and daywork.
A worked example
Item
Description
Unit
Qty
Rate
Amount
3.01
Plain cement concrete 1:4:8 under foundations, including curing
m³
42
17,500
735,000
3.02
RCC 1:2:4 in columns, including formwork and curing, excluding steel
m³
36
31,000
1,116,000
3.03
RCC 1:2:4 in slabs and beams, including formwork and curing, excluding steel
m³
110
28,500
3,135,000
Total carried to summary
4,986,000
Bill No. 3, Concrete (rates illustrative, PKR)
Notice that each description says what the rate includes (formwork, curing) and what it does not (steel). That one phrase decides, months later, whether formwork can be billed separately. Quantities for concrete and steel can be checked with the concrete calculator and the bar bending schedule calculator.
Rules for writing BOQ items
One item, one unit, one rate. Do not mix work measured in m³ and m² in one line.
Say what the rate includes and excludes: materials, labour, formwork, wastage, carriage, curing.
Measure net, as fixed, unless the method of measurement says otherwise; wastage belongs in the rate.
Use the specification and mix ratios that are in the drawings, not general ones.
Keep provisional sums and prime cost items clearly marked, so they are not mistaken for priced work.
Number items so a running bill can refer to them without ambiguity.
BOQ in Excel: where it starts to hurt
Almost every BOQ in Pakistan starts in Excel, and for the tender that is fine. The trouble starts after award. The client BOQ, the subcontractor BOQs and the running bills become separate files; a quantity revised in one is not revised in the others; and by the third bill nobody is sure which version the contract was signed on. Withholding tax and net receivable become formulas someone has to remember to copy.
One BOQ from tender to final bill
In Smart Construction the BOQ is kept as items with their units, quantities and rates, priced from your own rate library or imported from Excel. After award the same items carry progress, so running bills are worked out from them, and subcontractor BOQs are linked item by item to show margin and exposure. See BOQ software or book a demo.
Frequently asked questions
What are the columns in a BOQ?
Item number, description, unit, quantity, rate and amount. Running bills add columns for quantity up to the previous bill, this bill and up to date.
What is the difference between a BOQ and an estimate?
An estimate is the contractor’s internal working of cost: materials, labour, plant and overheads. The BOQ is the priced list of items the client sees and the contract is paid on. The estimate is how you arrive at the BOQ rates.
Who prepares the BOQ?
On most projects the client’s consultant or quantity surveyor prepares the unpriced BOQ from the drawings, and each contractor prices it. On design-and-build or private work the contractor may prepare it.
Can I prepare a BOQ in Excel?
Yes, and most do for the tender. The difficulty comes after award, when running bills, variations and subcontractor BOQs must stay in agreement with it, which is where BOQ software helps.
What IPC stands for in construction, who certifies it, and how the amount is worked out in Pakistan: work done, variations, advance, retention and tax.
How a running bill is laid out in Pakistan, what each column means, how the previous bill is carried forward, and the mistakes that get bills returned.