Retention money is the part of each bill the employer holds back as security that the contractor will put right any defects. It is the contractor’s money, earned and certified, simply paid later: part when the works are taken over, the rest when the defects period ends.
Because it comes back a year or more after the work, retention is the money contractors most often forget to collect. On a firm with several contracts it can add up to the profit of a whole job, sitting in other people’s accounts with nobody chasing it.
How much is held on Pakistani contracts
Form
Held from each bill
Limit
PEC 2023 works (FIDIC 2017)
7%
5% of the contract price
PEC 2007 civil works
10%
5% of the contract price
PEC 2007 smaller contracts
5%
Held until the defects period ends
Retention on PEC standard documents (check your own contract)
The limit matters as much as the percentage. At 7% of each bill with a 5% limit, retention stops being taken once about 71% of the contract has been billed; at 10% with the same limit, once half has. After that, bills carry no retention deduction at all. Private contracts set their own terms, and many simply hold 5% or 10% of every bill with no limit.
When retention comes back
Half when the engineer issues the taking-over certificate, which says the works are complete.
The other half when the defects period ends, 365 days later on PEC’s 2023 terms.
PEC’s form for smaller contracts pays it all within 14 days after the defects period.
If defects are still being put right when the period ends, the engineer can hold back what that remaining work will cost. That is why a defects list closed on time is worth money: it is what releases the second half.
A worked example
Bill
Gross this bill
Retention this bill
Retention to date
1
6,000,000
420,000
420,000
2
8,000,000
560,000
980,000
3
9,000,000
630,000
1,610,000
4
7,000,000
390,000 (limit reached)
2,000,000
5 onwards
any
nil
2,000,000
PKR 40 million contract, 7% of each bill, limit 5% (PKR 2,000,000)
On taking-over PKR 1,000,000 comes back; a year later, once defects are cleared, the last PKR 1,000,000. Work out your own figures with the retention money calculator.
Retention, performance security and tax
Performance security is a bank guarantee, 10% of the contract on PEC’s terms, given at the start. No cash changes hands unless it is called. Retention is cash kept back from each bill.
On PEC’s 2023 terms the performance security is halved at taking-over, at the same time as the first half of retention is released.
Income tax under section 153 is usually withheld on each bill’s full gross value, retention included, so nothing more is deducted when retention is released. Some employers deduct as they pay instead. Confirm with your tax adviser.
Why retention goes uncollected
Retention is released long after the site team has moved on, against certificates nobody is watching for. The taking-over certificate arrives, the first half is due, and no one asks. A year later the defects period ends on a date nobody wrote down. Across several contracts the unclaimed total grows quietly, and the subcontractors’ retention you hold is often just as poorly tracked in the other direction.
In Smart Construction retention is worked out on each bill from the contract’s own percentage and limit, the balance held is always visible per project and per client, and subcontractors’ retention is tracked the same way on their bills. See construction billing software or book a demo.
Frequently asked questions
What is the usual retention percentage in Pakistan?
PEC’s 2023 standard documents hold 7% of each bill up to 5% of the contract price; its 2007 civil works form 10% up to 5%; its form for smaller contracts 5%. Private contracts set their own, often 5% or 10% of every bill.
When is retention money released?
Usually half when the works are taken over and half when the defects period ends, typically a year later. Check the release clause in your own contract.
Is retention money the contractor’s income?
Yes. It is part of the certified value of work done, earned when the work is certified and simply paid later. It should sit in the books as money receivable, not be forgotten.
Can retention be replaced by a bank guarantee?
Some contracts allow the contractor to give a retention guarantee in exchange for releasing the cash retention. It depends on the contract’s particular conditions.
What IPC stands for in construction, who certifies it, and how the amount is worked out in Pakistan: work done, variations, advance, retention and tax.
How a running bill is laid out in Pakistan, what each column means, how the previous bill is carried forward, and the mistakes that get bills returned.
The standard layout of a bill of quantities in Pakistan, how items are grouped and measured, a worked example, and how the BOQ drives every running bill.