Running bill in construction: format, columns and a worked example
How a running bill is laid out in Pakistan, what each column means, how the previous bill is carried forward, and the mistakes that get bills returned.
Commercial
What IPC stands for in construction, who certifies it, and how the amount is worked out in Pakistan: work done, variations, advance, retention and tax.

IPC stands for Interim Payment Certificate. On a construction contract it is the document in which the engineer certifies how much the contractor is to be paid for the work done in a period, usually a month. The contractor asks for the money in a running bill; the IPC is the engineer’s answer, and it is what the employer actually pays against.
In Pakistan IPCs are standard on government and donor-funded work, which runs on the Pakistan Engineering Council’s standard documents built on FIDIC conditions, and common on larger private projects too. A contractor who understands exactly how an IPC is built gets paid faster, because a bill that already matches the certificate’s logic leaves the engineer little to argue about.
The contractor prepares the statement: quantities measured to date against each BOQ item, approved variations, and the deductions the contract sets. The engineer, the consultant appointed by the employer, checks the measurements on site and against the measurement book, then certifies the amount he agrees is due. The employer pays on the certificate, not on the contractor’s bill.
Under FIDIC-based contracts, PEC’s among them, the engineer has a fixed time to certify once the statement is received, and the employer a fixed time to pay. On PEC’s 2023 standard documents an IPC is normally paid within 28 days, and late payment carries financing charges at KIBOR plus 3% a year. Your contract’s particular conditions decide the exact periods, so read them.
Every IPC is cumulative: it values everything done since the start, takes off everything already certified, and pays the difference. That is what stops errors compounding, provided the previous figures are carried forward exactly.
| Line | PKR |
|---|---|
| Work done to date (BOQ items) | 18,000,000 |
| Approved variations to date | 1,200,000 |
| Gross value to date | 19,200,000 |
| Less retention, 7% (limit 2,500,000 not yet reached) | (1,344,000) |
| Less advance recovered to date | (2,450,000) |
| Net value to date | 15,406,000 |
| Less IPCs 1 to 3 | (11,100,000) |
| Amount certified on IPC 4 | 4,306,000 |
When the employer pays, it withholds income tax under section 153(1)(c) of the Income Tax Ordinance. For tax year 2026-27 that is 7.5% for a company and 8% for an individual or firm on the Active Taxpayers List, doubled for anyone not on it. Provincial sales tax on construction services, and the share the payer withholds, depends on where the work is. The contract tax calculator works out the cheque for a given bill; confirm your own position with a tax adviser.
A contractor with five running contracts has five sets of cumulative quantities, five advances being recovered and five retention balances. Kept in separate spreadsheets, one wrong cell carries forward for months. In Smart Construction the BOQ is held as items, progress is recorded against them, and each bill carries the previous figures forward itself, with retention, advance recovery and tax worked out on the same rules every time. See construction billing software or book a demo.
Interim Payment Certificate: the engineer’s certificate of the amount due to the contractor for work done in a period, normally monthly, before the final account.
The running bill is the contractor’s claim. The IPC is the engineer’s certificate after checking it. The employer pays the certified amount, which can be lower than the bill.
Yes. Each IPC values all work done to date and subtracts everything certified before, so the amount due is the difference. Errors in a previous IPC are corrected in the next one.
It depends on the contract. On PEC’s 2023 standard documents an IPC is normally paid within 28 days, with financing charges for late payment. Private contracts set their own terms.