Skip to content

Updated

Free calculator

House construction time calculator

How long a house takes to build in Pakistan, from the drawings to handover: the months on site for your covered area, storeys and finish, a stage by stage timeline, the month you can expect the keys, and the money each stage needs.

  • Build times as of September 2026
  • Answers as you type
  • Free, no sign-up

Calculator

Plan your build

Give the plot size and storeys, or the covered area from your drawings, then the finish, the crew and the month you start.

The house
225 sq ft to the marla
Measured in
Storeys
Typical for a 10 marla double storey: 3,300 sq ft, 1,650 a floor. Type the area on your drawings to use it instead.
About a month more: the digging, the retaining walls and the waterproofing come before anything else.
The build
Finish
Tiles, local wood doors, aluminium windows, emulsion paint and local sanitary ware.
Crew
One team of masons and labourers, as most houses get.
The month the drawings start, or work on site if the map is already approved.
Usually 1 to 2 months before work starts. Leave it empty if the map is approved.
Money for each stage
For the middle estimate at rates as of September 2026.
A builder's quote or your own figure, split in the same shares.

An estimate for planning, not a builder's programme. A real schedule comes from your drawings and the crew on site.

Time to build

On site, first dig to handover9 to 13 monthsFor a 10 marla double storey (3,300 sq ft covered) with a standard finish. Add 1.5 months before that for the drawings and the map approval.
Grey structure
4 to 6 monthsexcavation to plaster
Handover
Oct 2027 to Feb 2028drawings from December 2026
Before work starts
1.5 monthson site from January 2027
Money needed
Rs 1.95 croremiddle estimate, Lahore

The concrete and plaster work runs into the monsoon, June 2027. Rain holds up pours, plaster and roof work, so the high end allows a week more for it.

Money stage by stage

Excavation and foundationsJan to Feb 2027 · 10%
Rs 2,020,000
Ground floor frame and lenterFeb to Mar 2027 · 10%
Rs 2,020,000
First floor frame and lenterMar to May 2027 · 10%
Rs 2,020,000
Brick wallsMar to May 2027 · 10%
Rs 2,019,000
Pipes and conduitsMar to Jun 2027 · 7%
Rs 1,346,000
PlasterApr to Jun 2027 · 7%
Rs 1,346,000
RoofMay 2027 · 2%
Rs 449,000
FlooringJun to Sep 2027 · 11%
Rs 2,145,000
Wiring, tanks and pumpsJun to Sep 2027 · 6%
Rs 1,155,000
Doors, windows and woodworkJul to Oct 2027 · 14%
Rs 2,640,000
PaintSep to Dec 2027 · 5%
Rs 990,000
FixturesOct to Dec 2027 · 7%
Rs 1,320,000
Total
Rs 19,470,000

See the month by month timeline

Build times from builders' published timelines, the same as the house construction cost calculator. Money at its middle estimate, rates as of September 2026, without the land, approval fees and utility connections. A typical order of work, not a builder's programme.

Your build

Month by month timeline

A 10 marla double storey (3,300 sq ft covered) with a standard finish, starting December 2026: each stage at the middle of the range, overlapping as it does on site.

Drawings and approvalGrey structureFinishingHandoverJune to September, the monsoon
Stage by stage
StageWhenTakes
Drawings and map approvalDecember 2026 to January 20277 weeks
Excavation and foundationsJanuary to February 20273 weeks
Ground floor frame and lenterFebruary to March 20276 weeks
First floor frame and lenterMarch to May 20276 weeks
Brick wallsMarch to May 20272 months
Pipes and conduitsMarch to June 20272.5 months
PlasterApril to June 20272 months
RoofMay 20273 weeks
FlooringJune to September 20272.5 months
Wiring, tanks and pumpsJune to September 20273 months
Doors, windows and woodworkJuly to October 20273.5 months
PaintSeptember to December 20273 months
FixturesOctober to December 20277 weeks
Snagging and handoverDecember 20272 weeks

The shaded months are June to September, the monsoon. Bars show when a stage is under way, not that its crew works every day of it: the frame, for one, spends much of its time waiting for concrete to cure.

Reference

House construction time by plot size

Months on site from the first dig to handover for a double storey with the covered area a house on each plot usually has, worked out the same way as the calculator.

Double storey, standard finish, first dig to handover
HouseCovered areaGrey structureCompleteWith a large crew
3 marla1,200 sq ft2 to 4 months6 to 8 months5 to 6 months
5 marla2,000 sq ft3 to 5 months7 to 10 months5 to 8 months
7 marla2,650 sq ft4 to 6 months8 to 12 months6 to 9 months
10 marla3,300 sq ft4 to 6 months9 to 13 months7 to 10 months
1 kanal6,000 sq ft5 to 8 months12 to 16 months9 to 12 months

Standard finish, no basement. Add 1 to 2 months before work starts for the drawings and the map approval, about 1 month for a basement and about 2 for a premium finish.

Stage by stage

How a house is built, in order

Each stage as it runs on a 10 marla double storey with a standard finish, about 5 months for the grey structure and 6 for the finishing. Stages overlap, as they do on site.

  1. Drawings and map approval

    The architect's plans and the structural drawings, then the approval of your society or development authority: usually 1 to 2 months before any work on site. DHA Lahore's 2026 regulations give it 21 working days to check the drawings, and the clock starts again if they are sent back.

  2. Excavation and foundations

    Digging, the footings, the plinth and the damp-proof course: about 3 weeks.

  3. Frame and lenter, floor by floor

    Columns, beams and the slab (lenter) over each floor, about 6 weeks a floor, most of it waiting for the concrete to cure before the next floor goes on.

  4. Walls, pipes and conduits

    The brick walls start once the ground floor lenter is cast and take about 2 months. The water, drain and gas pipes and the electrical conduits go into them before they are plastered.

  5. Plaster and the roof

    Plaster inside and out takes about 2 months and completes the grey structure. On the roof, the mumty, the parapet, the insulation and the waterproofing take about 3 weeks.

  6. Floors and wiring

    Floor tiles or marble, and the bathroom and kitchen walls, about 2.5 months, while the electrician pulls the wires and fits the tanks and pumps.

  7. Doors, windows and woodwork

    Made in the carpenter's shop from the start of the finishing and fitted over about 3.5 months: doors, windows, grills, the kitchen and the wardrobes.

  8. Paint, fixtures and handover

    Putty, primer and paint over about 3 months, then the sanitary ware, taps, lights and switch plates, a snag list, the cleaning and the utility connections.

How it is worked out

From covered area to months

The months on site are the ones builders publish for houses they have built, set by the covered area: every floor, measured to the outside of the walls. A 5 marla double storey takes 7 to 10 months from the first dig to handover, a 10 marla 9 to 13 and a 1 kanal 12 to 16, with the grey structure taking 3 to 5, 4 to 6 and 5 to 8 months of that. Sizes in between are drawn along the same lines. These are the same figures as the house construction cost calculator, so the two agree.

A basement adds about 1 month, because the digging, the retaining walls and the waterproofing come before anything else can start, and a premium finish about 2 more for imported materials and detailed woodwork. A large crew, about half as many workers again with a second set of shuttering, cuts the grey structure by about 20% and the finishing by about 25%: concrete takes the same days to cure however many hands there are.

The timeline lays the stages out in the order a Pakistani site works, with the overlaps a real site has: the walls rise once the first lenter is cast, the pipes and conduits go into the walls before the plaster, and the doors and cabinets are made in the carpenter's shop while the floors are laid. It is drawn at the middle of the range. The months for the drawings and the map approval come first, if you give them.

The money for each stage is its share of the house construction cost calculator's estimate: the frame and slabs are the biggest part of the grey structure, the woodwork and the floors the biggest part of the finishing. Leave the budget empty to use the middle estimate for your city, or type your own figure or a builder's quote to split that instead.

Weather

The monsoon, the heat and the best time to start

June to September is the monsoon. Rain stops concrete pours, washes fresh plaster and mortar, and leaves a site too wet to work for a day or two, so builders plan the grey structure outside it where they can. The calculator checks which months your concrete, plaster and roof work fall in, and adds about a week to the high end for every month of it in the rains.

A start on site in any month from October to January gets a 10 marla double storey's grey structure up before June. For a 5 marla house the window is October to February, and for 1 kanal, which takes longer, October to November. The finishing can carry on through the rains, because most of it is indoors.

May and June bring the other problem: heat. Concrete that dries too fast loses strength, so slabs and columns need to be kept wet for longer and pours are best made early in the morning. Winter is the easiest season for concrete, and fog holds up little but the deliveries.

On site

Terms you will hear

Grey structure
The house without its finishes: foundations, frame, slabs, walls, plaster and the roof treatment, with the pipes and conduits in the walls. The first half of the build, and the part the weather can hold up.
Lenter
The reinforced concrete slab that roofs a floor, cast in one go on shuttering. A double storey has two, and a small one over the mumty.
Shuttering
The formwork of steel plates or wooden planks, on props, that holds wet concrete in shape. It stays under a slab until the concrete can carry itself, which is what sets the pace of the frame.
Curing
Keeping fresh concrete and plaster wet for the first days, so they set strong rather than dry out and crack. It cannot be hurried by adding workers.
Snag list
The list of faults and unfinished bits walked through before handover, from a door that sticks to a missing switch plate, that the builder puts right before handing over the keys.

For contractors, builders and developers

Built for contractors who run the whole job

Smart Construction keeps every project, site diary, purchase and payment in one place, on the web and on the phone your supervisors already carry.

  • Every site, its budget and its progress on one screen.
  • Site diaries, photos and attendance from the supervisor's phone.
  • Bills, payments and profit per project in PKR.

Book a demoContractor software

Also: Construction app · Petty cash software · Construction ERP software

Questions

Construction time questions

Building your own house?

Smart Construction is software for construction companies. We do not sell materials, quote rates or take building work, so our team cannot answer rate questions by phone or WhatsApp. The prices on this page are the latest published ones; for today's rate, ask your local supplier.

How long does it take to build a house in Pakistan?

From the first dig to handover, a 5 marla double storey takes about 7 to 10 months, a 10 marla 9 to 13 months and a 1 kanal 12 to 16 months with a standard finish. Add 1 to 2 months before that for the drawings and the map approval, about 1 month for a basement and about 2 for a premium finish.

What is the construction schedule for a 10 marla house?

About 9 to 13 months on site. Excavation and foundations take about 3 weeks, then each floor's frame and lenter about 6 weeks, with the walls, pipes and plaster following, so the grey structure is up in 4 to 6 months. The finishing takes the rest: floors, then woodwork, paint and fixtures, with a snag list and handover at the end. The calculator draws the whole timeline month by month from your start month.

How long does the grey structure take?

About 3 to 5 months for a 5 marla double storey, 4 to 6 for 10 marla and 5 to 8 for 1 kanal, from excavation to the end of the plaster. Most of it is the frame: each floor's lenter has to cure before the next floor goes on. A basement adds about 1 month, and a monsoon in the middle of it can add a few weeks.

How long does finishing take after the grey structure?

Usually a little longer than the grey structure: about 4 to 5 months for a 5 marla house and 5 to 7 for 10 marla with a standard finish, and about 2 months more for a premium one. It goes fastest when the tiles, doors, kitchen and fittings are chosen and ordered before the plaster is finished.

How long does map approval take?

Allow 1 to 2 months for the drawings and the approval together. The approval itself is set by your society or development authority: DHA Lahore's 2026 regulations give it 21 working days to check the drawings, restarting if they are sent back for changes, and the approved drawings stay valid for two years. The same regulations expect the house to be finished within two years of approval.

Does the monsoon delay construction?

Yes, the grey structure. Rain from June to September stops concrete pours and outside plaster, so the calculator adds about a week to the high end for every month of concrete and plaster work in the rains. A start on site in any month from October to January gets a 10 marla house's grey structure up before June.

How can I build my house faster?

Keep the money ready for each stage, choose the tiles, doors and fittings early, and agree with the builder on the crew. A large crew, about half as many workers again with a second set of shuttering, takes a 10 marla house from 9 to 13 months down to about 7 to 10 (5 to 8 for 5 marla, 9 to 12 for 1 kanal). Concrete still needs its days to cure, so the grey structure shortens less than the finishing.

When will I need the money during construction?

The grey structure takes about 58% of a standard house's cost, all in its first 4 to 6 months for a 10 marla house, with the frame and slabs the biggest single part. The finishing money follows over the rest of the build, most of it for the floors and the woodwork. The calculator shows each stage's money against its months.

Keep the build on schedule

Smart Construction plans the schedule and the milestones of every job, and keeps the work, the payments and the handover date on time.

For construction companies. We do not sell materials or quote rates.